Case Study: When a Missing Clause Delayed a Multi-Million Dollar Infrastructure Delivery
- Ibrahim Habib

- Nov 15
- 3 min read

How a supplier–contractor dispute over inspection rights nearly collapsed a cross-border project — and how structuring the contract properly saved it.
Background
A European supplier secured a contract to deliver specialised industrial equipment for an energy project in Iraq.
Both sides agreed verbally on quality standards, inspection procedures and delivery milestones — but these details were not properly reflected in the written contract.
The contract was a generic template:
drafted quickly
missing cross-border provisions
silent on pre-shipment inspection
vague on who carries risk at different stages
unclear on defect claims
no mechanism for dispute resolution
no reference to Iraqi conformity requirements
Everyone assumed it was “fine.”
Until the equipment reached the port.
The Legal Issue
When the shipment arrived in Iraq, the client refused to release final payment, citing:
lack of a pre-shipment inspection report
concerns over conformity
minor surface damage from transport
The supplier insisted:
inspection was not contractually required
any damage occurred after risk had passed
the buyer had no right to withhold payment
The contract wasn’t clear enough to support either side.
Legally, both had arguments — and that’s exactly the problem.
The dispute stalled the project for five weeks.
Every day meant:
penalties building
the site contractor delayed
equipment sitting at port accruing storage fees
tension escalating
lawyers drafting letters
commercial relationships deteriorating
All because the contract didn’t match operational reality.
CARMA Group’s Intervention
1. Contract Diagnostics
We carried out a clause-by-clause review, identifying:
ambiguous inspection rights
unclear risk transfer point
missing acceptance procedure
contradictory language around defects
no reference to Iraqi standards or conformity requirements
no mechanism for resolving deadlock without litigation
The core issue:
the contract was not written for a cross-border energy project.
2. Reconstructing the Commercial Framework
Instead of escalating into a formal dispute, we rebuilt the commercial terms in a way both sides could accept:
Introduced a retrospective inspection and acceptance procedure
Defined condition thresholds and allowable variances
Split responsibility for port damage based on risk transfer moments
Set clear payment triggers tied to measurable events
Confirmed required Iraqi conformity documents
Created a fast-track dispute resolution mechanism (strict timelines)
This created clarity where there had been none.
3. Legal–Operational Alignment
We coordinated between:
supplier legal counsel
client’s local legal team
the engineering contractor
customs clearance agents
insurance reps
The goal was simple:
align the legal positions with what was actually happening on the ground.
The biggest value was in translating between European legal expectations and Iraqi operational realities.
4. Negotiated Resolution
We structured a deal both sides accepted:
client released partial payment immediately
supplier issued additional documentation (non-admission basis)
independent inspection performed locally
remaining payment tied to verified technical functionality
both parties waived punitive claims
This avoided arbitration, litigation and a very public commercial fallout.
Outcome
Shipment released
Payments settled
Project resumed
Commercial relationship preserved
New contract template adopted for future cross-border work
Most importantly:
a multi-million dollar project avoided collapse over a preventable legal gap.
Key Lessons
Generic contracts are dangerous in cross-border delivery.
Inspection, risk-transfer and acceptance clauses must be explicit.
Iraqi conformity requirements should never be an afterthought.
Legal disputes often come from operational misunderstandings, not bad faith.
A contract only works if it reflects how the project actually operates.
Bottom Line
CARMA Group bridges the legal, commercial and operational gaps that cause UK–Iraq delivery failures.
With on-the-ground coordination and legal structuring, we help keep projects moving — even when the paperwork falls behind the reality.




Comments